Spectrum Health South Pavillion - Fixed MRI
Gaines Township, Michigan |
|
|
- $900,000 construction cost
- Engineering services for new fixed 1.5T MRI addition to the South Pavilion off-site surgical facility
- A temporary Mobile MRI dock was designed and constructed prior to starting the fixed MRI addition which was completed in 6 months
|
|
- Special vibration isolation foundation system for the MRI equipment
- Special copper shielding enclosure for the MRI room
- Mechanical systems provide for temperature and humidity, medical gases, and pre-action dry pipe fire suppression system
- Electrical systems include lighting design with motion detection, power distribution with branch circuiting, nurse call systems, music system, emergency generator power, security and fire alarm, and a DC dimming system
|
|